ANTICIPATED PROJECT SCHEDULE
 
Milestone Date Status
Notice to Proceed July 29, 2010 Issued
Baseline Hydrology Report January 2011 Accepted
Draft Alternatives Evaluation Report Spring/Summer 2012 In Progress
Final Alternatives Evaluation Report Summer 2012  
Draft Conceptual Design Report Fall 2012  
Final Conceptual Design Report Winter 2012