Timeline

Tentative Project Schedule

Deliverable/Milestone Completion Date Status
Notice to Proceed
11/17/2009
Underway
Draft Baseline Hydrology Report
6/9/2010
Completed
Final Baseline Hydrology Report
9/21/2010
Completed
Draft Alternatives Evaluation Report
12/2/10
Completed
Final Alternatives Evaluation Report
1/26/11
Completed
Draft Conceptual Design Report
7/18/11
Completed
Final Conceptual Design Report
9/8/11
Completed

For more information see Project Deliverables for descriptions and available downloads.

 