Timeline

Tentative Project Schedule

Deliverable/Milestone Completion Date Status
Notice to Proceed
12/3/2007
Proceeding
Baseline Hydrology Report
6/23/2008
Completed
Draft Alternatives Report
9/30/2008
In Progress
Final Alternatives Report
01/06/2009
 
Draft FHAD Report
06/02/2009
 
Draft Conceptual Preliminary Design Report
06/02/2009
 
Final FHAD Report
08/04/2009
 
Final Conceptual Preliminary Design Report
08/04/2009
 

For more information see Project Deliverables for descriptions and available downloads.

 