Timeline

Tentative Project Schedule

Deliverable/Milestone Completion Date Status
Notice to Proceed
12/3/2007
Proceeding
Baseline Hydrology Report
6/23/2008
Completed
Updated Baseline Hydrology Report
5/27/2009
Completed
Draft Alternatives Report
7/14/2009
Completed
Final Alternatives Report
10/8/2009
Completed
Draft FHAD Report
5/3/2010
Completed
Draft Conceptual Preliminary Design Report
5/18/2010
Completed
Final Conceptual Preliminary Design Report
9/10/2010
Completed
Final FHAD Report
Pending
In Progress

For more information see Project Deliverables for descriptions and available downloads.

 